Ask for offer

CCPP Brazi Rope Access & Painting

AlpAccess was the main coating services provider for the Combined Cycle Power Plant built by METKA and General Electric OMV Petrom in Brazi Prahova Romania.

Project Owners

Ge Logo
Petrom Logo
Metka Logo

Using our rope access skills we provided fast and safe protective coatings services for all the areas of the project, ranging from condenser lining, to stack and boiler exterior coatings.

We provided also PFP (passive fire protection) to the structures of Gas compressors and Lube oil buildings.

Half way of the project we started supplying scaffolding and by the end of the project we’ve supplied half of the total volume and all the commissioning scaffolding. The scaffolding was supplied in partnership with Huennebeck Romania (at that time Harsco infrastructure Romania).

CCPP Brazi is a combined cycle electric power plant of 860 MW, with two General Electric gas turbines and one steam turbine. The plant is built by Petrom and, when in full capacity, it covers almost 9% of the electricity demand in Romania.

Testimonials